2017 Road Improvement Plans for Carmel Announced

2017 Road Improvement Plans for Carmel Announced

Post Date:02/28/2017
carmel seal 2012 small 
City of Carmel
www.carmel.in.gov
One Civic Square, Carmel, IN 46032

NEWS RELEASE

Date: February 15, 2017
Contact: Nancy Heck (317) 571-2474
Release: Immediate

2017 Road Improvement Plans
for Carmel Announced

CARMEL, IN – The City of Carmel has a very aggressive construction schedule for 2017 and it will be important for you to plan ahead to make sure your regular routes are available and if not, to determine your best detour before you head out the door.

To help you stay connected, please take a moment to download the CarmelLink app so that you will have access to the latest road construction updates. Please note that the CarmelLink app requires the use of the Waze app, so you will be prompted to download that as well.

While we are providing a snapshot of projects planned for 2017, please remember there are many variables that affect the exact start and finish dates. We will send notices of closures or detours closer to the beginning of construction.

The projects below are listed under the month in which they will begin. There are various timelines for completion. For details, go to www.CarmelLink.com. Direct links are provided below when available.

2017 ROAD IMPROVEMENT PROJECTS

March
Main Street Drainage improvement, 4th Avenue SW to Guilford Road
Towne Road Trail, 96th Street to 106th Street
Lake Shore Drive East Culvert replacement, just South of 106th Street
106th Street Culvert replacement, Michigan Road to Shelborne Road
Greentree Drive Culvert replacement
Spring Mill Phase 2 boulevard reconstruction
126th Street improvement, Range Line Road to Keystone Avenue



April
River Road reconstruction, Community Drive to 146th Street
116th Street and Towne Road Roundabout
126th Street and Gray Road Roundabout
136th Street and Gray Road Roundabout
Gray Road Culvert replacement, south of 146th Street
Ditch Road Path Project, 106th Street to 116th Street
Range Line Road and City Center Roundabout

May
Old Town Alley and Storm Water improvements
Carmel Drive and City Center Drive Roundabout

June
96th Street and Delegates Row Roundabout
96th Street and Gray Road Roundabout
Guilford Road and City Center Drive Roundabout
106th Street and Towne Road Roundabout
116th Street and Hazel Dell Parkway Roundabout

July
Range Line Road reconstruction 136th Street to U.S. 31 overpass
Range Line Road and 136th Street Roundabout adjustment
4th Street NW reconstruction
5th Street NE curb construction

August
Range Line Road and 4th Street Roundabout
Guilford Road and Carmel Drive Roundabout
Monon Boulevard Construction, City Center Drive to Main Street

Fall 2017
96th Street and Hazel Dell Road Roundabout
Range Line Road and Executive Drive Roundabout
96th Street and Priority Way Roundabout
Carmel Drive and Old Meridian Street Roundabout
96th Street and Keystone Parkway interchange (preliminary work)
Gray Road and Main Street Roundabout
Range Line Road reconstruction, 116th Street to Main Street
Foster Estates drainage improvements
Main Street Path project, Harrowgate Drive to Cool Creek Court
Carey Road Path project, Hawthorne Drive to Edinburg Drive
Shelborne Road Path project, 106th Street to 116th Street

NEW
South West Clay Storm Water and Multi-use Path
Several multi-use paths are being added to the South West Clay area, as the City continues to make improvements set forth in the annexation agreement with this area. Nearly all of the work will happen off the roadway, primarily along Ditch Road, Towne Road and Shelborne Road. All these projects, including roundabout construction, will improve pedestrian connectivity and storm water mitigation in this area.

UPDATED
Crooked Stick Drainage / Storm Water and Multi-use Path
A variety of drainage issues in the crooked Stick area will be improved by this project, which will also include construction of multi-use paths on the west side of Ditch Road between 106th and 116th Streets. Storm drainage improvements also will be included as part of this project, which is expected to be completed by mid-July, 2017.

UPDATED
West Carmel Drive Path Project
One westbound lane on Carmel Drive will be closed during construction of a new path to connect U.S. 31 to Keystone Parkway, a project that began last fall. Expect lane restrictions to resume once weather permits construction to begin again. The path will link existing path along the north edge of West Carmel Drive, just west of 3rd Avenue to the intersection near North Clark Street. This portion of the city’s path project is expected to conclude in April, 2017.

UPDATED
126th Street Improvements between Range Line Road and Keystone Avenue
Road improvements have been underway, including multi-use paths and storm water management, since last year. In 2017, traffic will be maintained in the westerly direction for the duration of the project. This project is anticipated to last until summer of 2017.
Detour Route: Use Main Street and 116th Street for eastbound traffic. Keystone Parkway and Guilford Avenue will be main routes connecting drivers to eastbound detour routes.

UPDATED
Spring Mill Road Improvements
Beginning in March, Spring Mill Road will be closed between Millridge Drive and 106th Street for three months to reconstruct Spring Mill Road and replace a large culvert. Meanwhile, work that began last year will continue on Spring Mill Road and motorists should expect lane restrictions and closures.

CarmelLink 2.0 Update
CARMEL LINK 2.0 is a concentrated infrastructure improvement program that will result in the completion of new roundabout intersections along Gray Road, 96th Street, Range Line Road, 116th Street, Guilford Road, Pennsylvania Street, Spring Mill Road, Towne Road, Keystone Parkway with a new interchange at 96th Street, storm water management and drainage improvement projects throughout the City of Carmel. It will also include the upgrade of a large section of Range Line Road and other miscellaneous improvements over the next three-years.

-30-

Sign up for email alerts and updates at www.CarmelLink.com

For any remaining questions or concerns please contact City of Carmel Engineering Department at 317-571-2441 or email Engineering Administrator Joshua Kirsh at jkirsh@carmel.in.gov