► THE REQUIRED INSPECTIONS VARY WITH EACH PERMIT. Your
Improvement Location Permit (I.L.P.) application indicates those
inspections which have been assessed to your project. Be sure to
read the specific instructions on the inspection procedure sheet
you were given at permit issuance, for scheduling each type of
inspection.
► Your permit number will be required when scheduling.
► After the Footing and/or Under-slab inspections have been
approved, the BUILDING PERMIT PLACARD must be posted at all
times during construction. The placard must be located on a
front window, facing the street, or the inspection will not be
conducted and a re-inspection fee will be assessed. The placard
must be accessible for signature by the inspector.
► The PROPERTY OWNER (or their representative) MUST be present
for inspections of OCCUPIED structures. Call to schedule these
inspections a minimum of 24 hours in advance. An AM or PM window
will be given at scheduling, as someone will need to be on site
to meet the inspector.
► CANCELLATIONS must be called into the main office at: (317)
571-2444.
► For REMODELS & ADDITIONS, additional inspections may be
scheduled prior to the full final (if basic fire, life, and
safety items have been completed) to allow for furniture and/or
certain product to be placed in the space prior to the full
final inspection/approval.
► Additional fees may be charged, per ordinance, for additional
inspections that are scheduled, which were not part of the
original permit fee.